ROCHE DIAGNOSTICS - Germany

  • Detail Engineering
    Procurement
    Erection (Supervision)
    Commissioning (Support)
    Qualification (IQ, OQ)

HERCEPTIN PRODUCTION EXPANSION 254/10K - (H10) | 2006

Project completion time: 16 months


Delivery of a fermentation plant (H10). The production of herceptin required upgrading of the fermentation plant in Building 254.

This delivery included a fermentation rack with fermentation volumes of 20 L, 80 L, and 400 L and accessory equipment, as well as a 10,000 L bioreactor. In addition, the supply and disposal lines or transfer lines of the existing facilities were upgraded. Due to production-related reasons, remodeling was also needed for a flexible power supply in the ANSA cell facility and in the harvesting facility. Integration in the existing pipework system plus an extremely tight schedule made the project especially challenging.



VOGELBUSCH BIOPHARMA

Blechturmgasse 11, 1050 Vienna - Austria, P: +43 1 54 661 - 0, F: +43 1 54 661 - 100,
biopharma@vienna.vogelbusch.com, www.vogelbusch-biopharma.com